Qualify a second source in parallel, never by swapping it in. Start with a paper review of the drawing, specification and quality-system evidence, then validate samples with a first article inspection and material certificates, ask for capability data (Cpk) on the critical dimensions, and only then place one small guarded order while the incumbent keeps shipping. Volume moves only after that pilot passes.
Why a second source is a paperwork project first
A running part has two specifications. The first is the drawing procurement keeps on file. The second is the set of process decisions that make the part actually come out of a press consistently: which way the parting line runs, where the gate sits, what shrinkage was applied to each cavity, which compound and hardness were used, what cure and post-cure profile was set, and what the inspector calls a defect. That second specification is usually spread across emails, a tool card and an operator's habits rather than written down in one place. When a buyer sends only a 3D file to a candidate supplier, the candidate quietly rebuilds that second specification from scratch. Parts can still match the drawing and fail in assembly — which is why dual-sourcing projects so often take longer than a tooling lead time suggests.
The safe sequence is therefore: prove capability on paper, then on a sample, then on one small production lot. At every stage the incumbent keeps running. A candidate is not a second source until the new plant has shipped conforming product under the same criteria the incumbent is measured against.
Step 1 — qualify on paper before any steel moves
Paper qualification is the cheapest stage and the one most often skipped. Ask the candidate for the current released drawing revision and 3D data, a written specification covering material, hardness, tolerance class and appearance, the relevant quality-system certificates with numbers, scope and validity, and the inspection or control plan used on the incumbent part. For silicone the material conversation should be specific: food-contact compliance is demonstrated to FDA 21 CFR 177.2600 and LFGB §30/31, whereas skin-contact or biocompatibility claims belong to ISO 10993 and USP Class VI testing. These answer different questions and must not be used interchangeably — a food-contact declaration is not a biocompatibility report.
CYES holds ISO 9001:2015 (certificate 61120Q012) and ISO 13485:2016 (certificate 04724Q10000602). For the designated medical LSR molding and packaging areas, our ISO Class 7 cleanroom is supported by third-party report CR-2026-0714; consumer and baby products are not produced in that cleanroom. Ask for a certificate number, scope and issuing body rather than a logo on a website, and check which standard actually covers your part.
For a running programme the record set matters as much as the certificate. Request the tool-build dimensional report, the compound and colour master record, the press settings and the outgoing inspection criteria. Establish in writing who owns the tool and who may authorise a transfer before any cavity is moved. Our published policy is that paid tooling IP belongs to the customer, and we work NDA-first — files are reviewed only after the NDA is in place.
Step 2 — make the candidate prove it with samples
Paper review ends with a sample, not a promise. The first tangible evidence is a first article inspection (FAI): a full dimensional layout of first-off parts measured against every drawing dimension, with actual values recorded rather than simple pass or fail marks. Pair it with a material certificate for the compound lot and a hardness report. A useful discipline is to ask the incumbent and the candidate to measure the same ten parts, on the same revision, with the same method, and send the raw numbers. Comparison at the level of a verdict hides exactly the differences a second source is meant to reveal.
Sample timing is a practical way to judge whether a supplier can support a parallel route. CYES produces functional samples in 3–7 days, single-cavity mould samples in 7–15 days and steel multi-cavity mould samples in 15–20 days. That allows a paper review and first samples to run while the incumbent is still shipping. Engineers respond within 24 hours, so DFM questions do not turn into weeks of email.
Step 3 — ask for process capability evidence
A sample proves a tool can make one conforming part. It does not prove the process will keep doing so. For critical dimensions, ask for a capability study — Cpk — on a named part, tool, lot and measurement system, calculated from measured data rather than asserted in a brochure. CYES publishes measured Cpk of 1.24–1.68 across documented studies, including 1.24 on a medical LSR diaphragm. We are deliberate about publishing the whole range rather than only the best figure: a capability number without the part, cavity and measurement method attached is not evidence.
Tooling contributes to that capability. Our in-house MAKINO CNC holds mould cavities to ±0.008 mm, which is the baseline a second-source first article is measured against. When a drawing or quality plan calls for an independent CMM or blue-light scan, agree the laboratory and the method before parts are compared. Changing the measurement system mid-qualification invalidates the comparison and is a common reason two suppliers appear to disagree when they do not.
Step 4 — one guarded pilot order
The final qualification step is deliberately small. Run one order at real production conditions, inspect it to the agreed outgoing standard, and check the documentation that travels with it — dimensional report, material lot traceability and any certificates your quality plan requires. Only after that order has shipped and been received should volume shift. CYES supports this stage with a 100-piece minimum order and published price tiers at 500, 1,000 and 5,000 pieces, so a guarded pilot does not require committing to full production volume up front. Our on-time delivery rate is 98% and 83% of our orders come from repeat customers; that is the sort of record worth checking on a second source as well as on an incumbent.
Tool transfer — settle ownership before anything moves
Moving an incumbent tool is the fastest way to stop the incumbent. If a transfer is eventually required, it should be the last step, not the first: qualify the new plant from released data or from a second tool, and only transfer steel once that plant can produce conforming parts consistently. Confirm the tool record — cavity layout, gate and vent details, steel grade, maintenance history and the last dimensional report — and confirm who is authorised to release it. Under our policy the customer owns paid tooling and IP stays with the customer under NDA, so a transfer discussion should begin with that fact in writing, not with a truck booking.
What to compare between the incumbent and the new source
Compare like with like. Use the same drawing revision, the same measurement method and the same acceptance criteria, then compare raw dimensional data, defect classes, lot traceability and the documents delivered with each shipment. A revealing question is what each supplier does when a dimension drifts: the answer shows whether the quality system is real or decorative. For medical parts, also confirm that the cleanroom and process-validation statements apply to the exact plant that will run your component — “same part, different plant” is not the same claim as “same part, same line.”
Keep the comparison documentary. Agree in advance which dimensions are critical, which are reference only, and what measurement system will be used for each; then require both suppliers to report actual values for the same lot size. A candidate that can only supply pass/fail labels has not really been qualified, and a difference discovered after the first volume shipment is an expensive way to learn the inspection criteria were never aligned.
When not to dual-source
Dual sourcing is not free. It adds a second set of tools, a second qualification file, a second relationship and sometimes a second kind of process variation. For very low volumes, one well-qualified supplier with a documented contingency plan can be cheaper than two. Avoid dual sourcing when the part is still changing in design, when the volume cannot support two tools, when regulatory approval ties the component to a specific validated line, or when the candidate cannot match the incumbent's inspection and traceability requirements. In those cases, reduce the single-source risk in other ways — safety stock, a documented capacity plan, or a second tool held off-line — rather than adding a supplier that is not truly qualified.
CYES as a practical second source
A good second source is not necessarily the largest factory; it is the one that can prove a part without disrupting the current one. CYES is a 10,000 m² factory with 261 employees, founded in 2004, with in-house mould making, compression moulding and LSR injection. Our low-MOQ programme and short sample cycles are useful precisely because a second-source trial is small by design: 100-piece pilots, engineering samples in days, and an NDA signed before files are reviewed. We do not claim a qualification we cannot support — we show certificate numbers, capability data and measured cavity tolerance, and we let the customer's method decide whether the parts pass.
The discipline is simple: paper first, samples second, capability third, one guarded order last. Keep the incumbent running until the end. If a candidate will not work to that sequence, it is usually telling you something important.