Lead time is counted from final drawing and DFM approval. SLA/DLP prototypes take 1–3 days; rapid samples from existing tooling 3–7 days; a new single-cavity mold 7–15 days; a steel multi-cavity production mold 15–20 days. Medical or complex LSR is confirmed per mold and validation requirements.
Lead times, by stage
| Stage | Lead time |
|---|---|
| SLA / DLP appearance prototype | 1–3 days |
| Rapid sample from existing tooling | 3–7 days |
| New single-cavity mold sample | 7–15 days |
| Steel multi-cavity production mold | 15–20 days |
| Medical / complex LSR | Per mold & validation requirements |
What "counted from approval" really means
The clock starts when the drawing and DFM are signed off — not when you first email us. Unresolved DFM questions, late drawing changes or pending material approvals add time that is not in the number above. The fastest projects are the ones where DFM closes in one round.
Why a realistic lead time protects you
A supplier promising a production mold in "5 days" is usually quoting a soft prototype mold that will degrade in a few hundred shots, not a production steel tool. We quote the real number so your launch date holds. See tooling lead time for the mold-building detail.