A silicone mold is built in days to a few weeks depending on complexity: a simple single-cavity compression tool in about 7–15 days, a multi-cavity or cold-runner LSR tool in 15–20 days or more, plus a few days for first-article sampling. Prototype routes are faster — SLA or DLP prints in 1–3 days, vacuum-cast parts in 3–7 days.
Lead time by route
| Route | Typical lead time |
|---|---|
| SLA / DLP prototype | 1–3 days |
| Vacuum-cast parts | 3–7 days |
| Single-cavity compression tool | 7–15 days |
| Multi-cavity / cold-runner LSR | 15–20 days+ |
What adds time
- Cavity count — each cavity is machined, polished and vented.
- Side actions and slides add fitting time.
- Texture and high polish add finishing steps.
- Cold-runner systems add assembly and tuning.
The fastest path is to run DFM and steel in parallel with your drawing sign-off, and use a prototype route to keep momentum while the production tool is cut.