Short answer

End to end, expect roughly 3–5 weeks for a new custom silicone part: DFM and tooling (1–3 weeks), first-article sampling (a few days), and production (days to a couple of weeks depending on volume). Simple single-cavity parts move faster; multi-cavity cold-runner tools and overmolding add time. Prototypes can ship in 1–7 days while steel is built.

End-to-end lead timeDFM through production.DFM1–3 dtool build7–20 dsampling2–5 dproduction5–15 dEnd to end ≈ 3–5 weeks.Sign DFM fast — approval latency, not machining, is the real delay.
DFM → tool build → first-article sampling → production, roughly 3–5 weeks end to end; approval latency is the real delay.

The end-to-end timeline

StageTypical
DFM + drawing sign-off1–3 days
Tool build7–20 days
First-article sampling2–5 days
Mass production5–15 days

What to do in parallel

  • Send a complete 2D/3D drawing with volume and target date on day one.
  • Sign the DFM the same day it arrives.
  • Pre-agree shipping and Incoterms so nothing waits at the end.

The biggest lead-time loss is not machining — it is approval latency. Every day the drawing or DFM sits unsigned is a day added to delivery.